Merton Civic Centre Replacement Windows

Hazlemere Commercial has many years of experience with Sapa, Comar & Reynaers products, which they fabricate to client requirements in their own 38,000 square feet production facility on Cressex Business Park, in the outskirts of High Wycombe in Buckinghamshire.

Hazlemere Commercial has rightly gained an enviable reputation with commercial  contracts like the £2.5m window refurbishment for the London Borough of Morden, where its ability to safely undertake the work while safe guarding the occupants, its staff and visitors was second to none.

Hazlemere Commercial acted as Principal Contractor on this substantial replacement aluminium fenestration project which involved the complete refurbishment of the external façade to a 14 storey tower building with a further two 2 storey wings.

The project involved the replacement of approximately two thousand 53 year old windows, cleaning of the external brickwork and mosaic tile façade, upgrade of lightning conductors, external redecoration, internal redecoration of two fire exit stairwells and the replacement of 14,000 square metres of suspended ceiling tiles .

Merton Civic Centre was “encased” in 420 tonnes of scaffolding after an independent glass and glazing consultant deemed the original single glazed steel framed windows as “unfit for purpose”. As part of the replacement windows  contract, Hazlemere Commercial recycled all the old steel windows, then replaced them with highly thermally efficient aluminium double glazed windows, manufactured from 100% recycled aluminium billet. The Sapa top swing reversible windows Hazlemere Commercial fitted enable each window to be cleaned safely.

Project – Merton Civic Centre
Location – Morden, London
Building Use – Local Authority Council Offices
Client – Borough of Merton and Morden
Products Used – Sapa Dualframe 75SI Top Swing Reversible Aluminium Windows, Sapa Dualframe 75Si Casement Windows
Value – £2,500,000 + VAT